The first 90 days: technology readiness for a new GCC

A week-by-week plan to get network, security, devices and support live before your first employees walk into your new GCC in India.

Shubham Malik, founder of SRD Corp, at his desk in the Gurgaon office

Written by Shubham Malik, Founder and CEO

Updated October 2026 · 7 min read

Why technology sets the critical path

Legal setup and hiring get the attention, but technology often decides whether day one works. Internet circuits, firewall approvals from HQ security, imported hardware and identity integration all have lead times that can't be compressed at the last minute.

The plan

  1. 1

    Weeks 0-2: Requirements and design

    Confirm headcount by role and month, HQ security and identity standards, and the site plan. Produce the network design, device standards and bill of materials. Order internet links immediately.

  2. 2

    Weeks 2-6: Procure and build

    Place OEM orders, start structured cabling and comms-room build, and set up firewall, switching and Wi-Fi. Agree on the approach for identity and SSO with HQ (shared tenant or a new one).

  3. 3

    Weeks 6-10: Configure and integrate

    Connect to HQ through SD-WAN or VPN, configure security policies, stage and image devices with asset tags, and set up meeting rooms and physical access control.

  4. 4

    Weeks 10-12: Test and go live

    Run user acceptance tests, a security review and a failover test. Launch the service desk, deliver role-based device kits, and provide hypercare for the first weeks.

Timelines are typical for a 50-300 seat centre in a ready building. Managed seats or an existing office can shorten the plan considerably.

Bill of materials checklist

AreaWhat to plan for
Per employeeLaptop, monitor, dock, headset, mobile device policy, software licences
NetworkTwo diverse internet links, firewalls in HA pair, core and access switches, Wi-Fi access points, structured cabling
Comms roomRacks, UPS, cooling, environmental monitoring, physical access
SecurityEndpoint protection, MDM, identity and MFA, email security, logging and SOC integration
CollaborationMeeting room systems, town-hall AV, digital signage
Physical securityAccess control, CCTV, visitor management
OperationsService desk, monitoring, asset register, AMC and warranty tracking

Common pitfalls

  • Ordering internet links late, when they are frequently the longest lead-time item
  • Waiting for HQ security sign-off on firewall and identity design until the last week
  • Buying devices without a standard image, so every laptop is set up by hand
  • No asset register from day one, which makes audits and refresh planning painful
  • Treating physical security as a facilities task instead of integrating it with IT and HR