What a GCC in India actually costs: a transparent per-seat model

Published GCC cost figures contradict each other because almost none of them show their workings. This guide gives the model instead of a number, with every assumption stated and every external figure sourced, so you can put your own inputs in and get a budget you can defend.

Shubham Malik, founder of SRD Corp, at his desk in the Gurgaon office

Written by Shubham Malik, Founder and CEO

Updated November 2026 · 11 min read

Why published GCC cost figures disagree

Search for the cost of a GCC in India and you will find confident numbers that do not agree with one another. One guide puts a lean centre of 10 to 25 people at 150,000 to 350,000 US dollars in year one. Another puts a 10 person centre at 400,000 to 700,000 dollars. Both cannot be describing the same thing.

They are not. The figures differ because the writers are measuring different things and rarely say which. Some include one-time setup and some do not. Some include statutory on-costs and some quote bare salary. Some assume a managed office and some assume a leased floor with a fit-out. Almost none state the salary band they used. Since salary is 60 to 70 percent of the total, an all-in number without a stated salary assumption carries very little information.

So this guide does not give you a number. It gives you the model, states every assumption, and sources every external figure. Put your own salary band in and the answer is defensible to your CFO. That is the part the other guides leave out.

The model

The annual cost of a seat is the sum of five things. Four are reasonably predictable. One dominates and is specific to you.

  1. 1

    1. Salary

    The dominant term, 60 to 70 percent of total spend. Entirely dependent on role, seniority and city. You must supply this.

  2. 2

    2. Statutory employer on-costs

    Provident fund, pension, insurance and gratuity provisioning. Set by law, so knowable in advance.

  3. 3

    3. Workspace

    Rent, common area maintenance, facilities and amortised fit-out. Driven by city rent per square foot and the area you allow per seat.

  4. 4

    4. Technology

    Endpoint, network, security licensing and a share of shared infrastructure. Largely a procurement question.

  5. 5

    5. Running the entity

    Accounting, payroll, statutory filings, audit and company secretarial work. Broadly fixed, so it falls sharply per seat as the centre grows.

These scale differently. Statutory and per-seat technology are roughly linear per head. Workspace is linear but steps up when you take the next floor. Entity running cost is close to fixed. That is why cost per seat falls as a centre grows, and why a 20 seat centre is not a fifth as expensive as a 100 seat one.

Input 1: statutory employer on-costs

These are set by statute, so unlike salary they can be stated with confidence. They apply on top of the salary you pay.

ComponentEmployer rateApplied toNotes
Provident fund (EPF and EPS)12%PF wagesSplits roughly 3.67% to EPF and 8.33% to the pension scheme
EDLI and administrationabout 0.5%PF wagesInsurance and admin charges on top of the 12%
Employees State Insurance3.25%Gross wagesOnly for employees under the earnings ceiling, so often not applicable to engineering roles
Gratuity provisioningabout 4.81%Basic pay15 days of wages per completed year, payable after five years. A provision, not a monthly payment

For a typical engineering GCC, where most salaries sit above the ESI ceiling, budget roughly 13 percent of PF wages plus gratuity provisioning. The common shorthand of 15 to 22 percent on top of salary is defensible at the lower end for senior teams and at the higher end where ESI applies across the workforce.

Two things to verify with your CA rather than take from any guide, including this one. First, the EPF wage ceiling: secondary sources disagree on whether it remains at 15,000 rupees a month or has risen to 25,000, which materially changes the cash cost. Second, salary structuring, because what counts as PF wages depends on how basic pay is defined, and rules on minimum basic as a share of total remuneration affect the answer.

Input 2: workspace

Workspace cost is rent per square foot, multiplied by area per seat, plus common area maintenance and facilities, plus fit-out amortised over the lease. The rent component is publicly measured, so start there.

CityAverage office rent, rupees per sq ft per monthYear on year
Delhi NCRabout 105Crossed 100 for the first time
Bengaluru100.6Up 7 percent
Pune80.9Up 5 percent
Hyderabad77.5Up 8 percent
Chennai74.5Up 8 percent

Those are Knight Frank Q1 2026 averages. Read them carefully, because the distinction matters more than the number. These are averages across a city, not prime rents and not quoted rents. A separate report lists Bengaluru market rent at 132.6 rupees, which is not a contradiction but a different metric. They also exclude common area maintenance and property taxes, which are charged on top.

Area per seat is the assumption that quietly doubles budgets. Dense floor plates can work at 60 to 80 square feet per seat. A centre with meeting rooms, labs, collaboration space and circulation will land nearer 100 to 125. Decide this explicitly rather than inheriting it from a template, and note that a hybrid attendance policy changes the seat count, not the area per seat.

Budget the deposit separately from running cost. Traditional Indian commercial leases commonly require six to ten months of rent as a security deposit, which is a cash flow event at signing rather than an expense. Managed and serviced offices trade a higher monthly rate for a much smaller deposit and a faster start, which is often the right trade for a first centre.

Input 3: technology

Technology splits into per-seat cost and shared infrastructure. The per-seat part is mostly procurement: laptop or workstation, monitors, headset, and per-user licences for identity, endpoint protection, collaboration and VPN. It is predictable once you fix the standard build, and it is the line where a quote today is worth more than any published range.

Shared infrastructure is where estimates go wrong, because it does not scale with headcount in a straight line. Network links, firewalls, switching, wireless, servers or cloud footprint, backup and the security stack are largely a function of the site, not the seat count. The first seat carries most of this cost and the hundredth carries almost none, which is the single biggest reason small centres look expensive per seat.

Two decisions move this number more than any vendor negotiation. Whether you buy or lease the endpoint estate, which is a cash flow and refresh cycle choice rather than a cost choice. And whether the centre needs its own compute on site, or can run on the parent cloud tenancy, which is the difference between a data centre line item and a connectivity line item.

Lead time is a cost that never appears in a spreadsheet. Enterprise hardware imported to order can add weeks between a signed lease and a working floor, and an empty fitted-out office still accrues rent and salaries. Sourcing from stock already held in India removes that gap.

Input 4: running the entity

An Indian subsidiary carries a standing compliance load whether it employs five people or five hundred: bookkeeping, monthly and quarterly statutory filings, payroll processing, TDS, GST, annual audit, board and company secretarial work, and transfer pricing documentation where the centre bills the parent.

Treat this as a largely fixed cost. That matters for the comparison most companies actually face. At ten people it is significant per seat and an Employer of Record often wins on economics. At a hundred people it is close to noise and ownership wins. The crossover is a real number you can calculate, not a matter of preference.

Transfer pricing deserves its own line. A GCC usually bills the parent on a cost plus basis, and the margin applied has to be defensible to Indian tax authorities. Agreeing the method early is far cheaper than defending it later.

One-time costs, which are not part of the per-seat figure

Keep these separate from running cost, because mixing them is exactly how published figures become incomparable.

  • Incorporation, including parent documents notarised and apostilled, which is usually the longest lead item
  • Statutory registrations: PAN, TAN, GST, PF, ESI, professional tax and Shops and Establishments
  • Security deposit on the lease, commonly six to ten months of rent
  • Office fit-out, which varies enormously with specification and is often amortised over the lease rather than expensed
  • Initial technology build: network, security and endpoints for the first cohort
  • Recruitment cost for the founding team, which is disproportionately senior and therefore disproportionately expensive

How to use this

  1. 1

    Fix the roles and the band

    Decide the actual roles and seniority mix, then get current salary data for those roles in your chosen city. This is 60 to 70 percent of the answer, so it deserves most of the effort. Do not take a salary figure from a vendor blog, this one included.

  2. 2

    Add statutory on-costs

    Apply the rates above to your salary structure, and have your CA confirm the PF wage treatment for that structure.

  3. 3

    Choose the workspace model explicitly

    Managed office or leased floor, and your area per seat. Multiply by city rent, then add common area maintenance and amortised fit-out.

  4. 4

    Quote the technology

    Split per-seat from shared and get a real quote for both. Shared infrastructure is why your per-seat cost at 25 people looks nothing like it does at 150.

  5. 5

    Add the fixed entity cost, then divide

    Add the annual compliance and audit load, then divide the total by seat count. Run it again at double the headcount to see how quickly the per-seat number falls.

Done honestly this produces a range rather than a figure, and a range with stated assumptions is far more useful to a board than a single number with hidden ones. If the range comes out uncomfortably wide, the width is telling you which assumption to go and verify first.

Context: the market you are entering

For scale, the Nasscom and Zinnov GCC Value Orbit report published in May 2026 counts 2,117 GCCs in India operating across 3,728 units, with revenue of about 98.4 billion US dollars in FY26 and a headcount the report itself labels an estimate, at roughly 2.36 million professionals. Around 506 Forbes Global 2000 companies run a centre here, alongside 583 mid-market and 504 private equity backed centres.

The mid-market figure is the relevant one for most companies reading this. The model above is not reserved for centres of a thousand seats. Most new centres are far smaller, and for them the fixed costs and the shared infrastructure decisions carry much more weight than headline salary arbitrage.

Sources

  • Office rents: Knight Frank India office market data for Q1 2026, as reported in the trade and business press. Figures are city averages excluding common area maintenance and taxes.
  • Statutory rates: EPF, EPS, EDLI, ESI and gratuity provisions under Indian law. Confirm current rates and the EPF wage ceiling with EPFO and your CA before budgeting, as the ceiling is disputed across secondary sources.
  • Market size: Nasscom and Zinnov, India GCC Landscape Report 2026 (GCC Value Orbit), May 2026, as reported in trade press. The headcount figure is an FY26 estimate.
  • Salary, technology and fit-out: deliberately not quoted here. These are specific to your roles, your build standard and your specification, and any published range would be guesswork presented as fact.

This guide is general information, not legal or tax advice. Rules and dates change; confirm the position for your company with SRD Corp's CA and legal partners before acting.