GCC Setup & Operations
Workspace & Facilities
We find, design and run the workplace your teams need: managed seats while you ramp up, then a custom fit-out with the IT, AV and security your HQ expects. Because we also build the technology, the space and the network are designed together.
What's included
How we help
Location & site search
Micro-market analysis, building shortlists, site visits and lease negotiation support.
Managed & flexible office
Plug-and-play seats in quality business parks while you ramp up.
Design & build
Workplace strategy, interior design, branded fit-out and project management.
Facility management
Housekeeping, front desk, cafeteria, maintenance and vendor management.
Employee transport
Shift transport with safety and compliance controls, including women-safety protocols.
Physical security
Access control, CCTV and visitor management, integrated with your IT and identity systems.
Managed office or your own lease is a question about certainty
A managed or serviced workspace gets you operational quickly, converts a capital project into a monthly cost, and lets you change size without renegotiating a lease. For a centre whose headcount plan is genuinely uncertain, that flexibility is worth paying for.
A conventional lease with your own fit out costs more up front and less per seat over time, and gives you control over the things that are hard to retrofit: power provisioning, server room location, cabling routes and access control. For a centre that knows its shape and intends to stay, it is usually the better economics.
Many centres do both deliberately, starting managed and moving into their own space once the headcount plan has survived contact with reality. The mistake is signing a long lease for a number nobody is confident about.
Read the building for power and cooling before the finishes
Fit out discussions tend to start with layout and finishes, because those are the visible decisions. The constraints that actually determine whether the space works are less visible: how much power the landlord will commit to your floor, whether there is somewhere acceptable to put a server room, what the generator and UPS arrangements really provide, and how much heat the building can reject.
A floor that is excellent for desks can be unsuitable for the infrastructure the centre needs, and discovering that after signing turns into either an expensive building services variation or a compromise you live with for the length of the lease.
So the technical survey belongs before the lease is signed, not after. It is a short piece of work and it is the cheapest point at which to find out.
Fit out and IT share one critical path
Running the workspace project and the technology project as separate workstreams with separate suppliers is the most reliable way to miss a go live date. Cabling has to be in before ceilings close. The server room needs power and cooling before equipment can be racked. Access control, surveillance and network all depend on the same containment and the same cabling.
When those are coordinated by different parties, the failure is predictable: each is individually on schedule and the sequence between them is nobody's responsibility, so the dependency surfaces as a delay that neither owns.
We run them as one programme with one critical path for exactly this reason. It is also the clearest practical argument for a single partner covering both.